Hughes Proposal onstruction Corporation PROJECT: Hickman County High School Date: SQ. FT.: LOCATION: DESCRIPTION: We are replacing range hoods with over-range microwaves. The range hoods that we replaced were all run on one circuit. With the addition of the two mocrowaves, this set up will not work, each microwave needs to have its own circuit. This change order is to add two circuits to accommodate the new over-range microwaves. PREPARED FOR: ITEM QUAN UN Labor M S LABOR MATERIAL SUB TOTAL Unit $ Unit $ Unit $ Adding 2 circuits 1 $ 750.00 $ - $ - $ 750.00 $ 750.00 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ # $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Total Labor $ - $ - Total Material $ > $ - - 25.0% Labor Burden > $ - 9.5% Sales Tax > $ - Subtotal GC Work > $ - Approved Total Subcontract $ 750.00 $ 750.00 Subtotal $ 750.00 Date 5.0% Overhead $ 37.50 Subtotal $ 787.50 10.0% Profit $ 78.75 Subtotal $ 866.25 5.0% BOND $ 45.59 Total Cost $ 911.84 2426 Madison Street / Suite 2 Clarksbille, TA 37043 Phone: 931-266-0233 mmm.hugjesconstructiontn.com ## Table 1 | PROJECT: | Hickman County High School Date: | | --- | --- | | SQ. FT.: | | | LOCATION: | | | DESCRIPTION: | We are replacing range hoods with over-range microwaves. The range hoods that we | | | replaced were all run on one circuit. With the addition of the two mocrowaves, this set up | | | will not work, each microwave needs to have its own circuit. This change order is to add | | | two circuits to accommodate the new over-range microwaves. | | | | | | | | PREPARED FOR: | | ## Table 2 | ITEM | QUAN | UN | Labor Unit $ | M Unit $ | S Unit $ | LABOR | MATERIAL | SUB | TOTAL | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | Adding 2 circuits | 1 | | | | $ 750.00 | $ - | $ - | $ 750.00 | $ 750.00 | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ # | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | | $ - | $ - | $ - | $ - | | | | | | | Total Labor | $ - | | | $ - | ## Table 3 | Total Material | $ - | > | $ - | | --- | --- | --- | --- | | 25.0% | Labor Burden | > | $ - | | 9.5% | Sales Tax | > | $ - | | | Subtotal GC Work | > | $ - | | | Total Subcontract | $ 750.00 | $ 750.00 | | | | Subtotal | $ 750.00 | | 5.0% | Overhead | | $ 37.50 | | | | Subtotal | $ 787.50 | | 10.0% | Profit | | $ 78.75 | | | | Subtotal | $ 866.25 | | 5.0% | BOND | | $ 45.59 | | | Total Cost | | $ 911.84 |