AIA® Document G701° - 2017 Change Order PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: East Hickman High School Contract For: Contruction Change Order Number: 002 Agricultural/Vocational Building 7700 TN-7 Date: 10-24-2025 Date: 01-06-2026 Lyles, TN OWNER: (Name and address) ARCHITECT: (Name and address) CONTRACTOR: (Name and address) Hickman County Schools Lyle Cook Martin Architects Fellowship Construction 114 North Central Avenue, Suite 203 310 Franklin Street 2668 Spencer Mill Road Centerville, TN 37033 Clarksville, TN 37040 Bon Aqua, TN 37025 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives.) See attached itemization. Addition of $17,467.84 to the Contract Sum. The original was $ 580,000.00 The net change by previously authorized Change Orders $ 5,433.92 The prior to this Change Order was $ 585,433.92 The will be increased by this Change Order in the amount of $ 17,467.84 The new including this Change Order will be $ 602,901.76 The Contract Time will be unchanged by Zero (0) days. The new date of Substantial Completion will be NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. BnodA.Martin Martin m ARCHITECT (Signature) CONTRACTOR (Signature) OWNER (Signature) Bradley A. Martin, III (Printed name Irwin and title) Pres. (Printed name, title, and (Printed name and title) license number if required) January 6, 2026 1-08-2026 Date Date Date AIA Document G701 - 2017. Copyright © 1979, 1987, 2000, 2001 and 2017. All rights reserved. "The American Institute of Architects," "American Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 15:50:02 1 CST on 01/06/2026 under Subscription .20250156901 which expires on 08/29/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (695d638e88670f656fd1a995) LYLE- COOK MARTIN ARCHITECTS Project No. 1402.1 East Hickman High School Agriculture/Vocational Building 7700 TN-7 Lyles, TN January 6, 2026 Change Order #02 1. Relocate Gas Add $9,561.68 2. Relocate Electrical Add $7,906.16 Total Add: $17,467.84 01 26 54 - FORM FOR PRICE SUMMARY SBC Project Number: Project Name: East Hickman Vocational Building Name of General Contractor: Fellowship Construction Proposal Number: RFP 2 Date Itemized: 2-Jan-26 Page of pages Work by Subcontractors Name of Subcontractor Costs and Allowances Move Conduit for exsiting light poles Optimal Electric 5,969.89 Add another 2 inch conduit in trench Optimal Electric 1,076.60 Subtotal: 7,046.49 General Contractor mark-up on Subtotal: 10.0000 % = 704.65 Subtotal for General Contractor for work by subcontractors: 7,751.14 Work by General Contractor Subtotal (including Subcontractors and the General Contractor): 7,751.14 Cells with red underline (if viewed in color) Bond Premium: 2.0000 % = 155.02 are for you to fill in. Others are protected. Rounding off is permitted if rounding up for decreases and rounding down Total: 7,906.16 for increases. Math functions in Excel show rounded to nearest penny, but carry exact value for calculations. Let embedded math do its work. This spreadsheet is available on the Owner's Designers' Manual website. TN Higher Education - Standard Document - May 2018 Page 1of 1 CHANGE ORDER COST ITEMIZATION Project Number: East Hickman Ag Barn CO-1 Work itemized below provided by: McLain Bryant Proposal Number: Page 1 of Pages Description Material Equipment Labor Qty Unit Cost Extension Qty Unit Cost Extension Qty Unit Cost Extension extra 2" conduit in the ditch with the 2-2" already speced in the drawings 1 652.00 652.00 0.00 0.00 Labor to install (Electrician 2) 0.00 0.00 4 47.43 189.72 0.00 0.00 0.00 existing pole lighting conduit outside the new facility footer 1 1,364.00 1,364.00 0.00 0.00 Electrician 1 0.00 0.00 16 65.95 1,055.20 Electrician 2 0.00 0.00 12 47.73 572.76 Mini ex/Skidsteer 0.00 1 1,803.00 1,803.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0,00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 0,00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Materials Subtotal 2,016.00 Equipment Labor Subtotal 1,817.68 9.5 % Sales Tax 191.52 15 % Burden 272.65 Cost 2,207.52 Cost 1,803.00 Cost: 2,090.33 Subtotal of Costs of Materials + Equipment + Labor = 6,100.85 10% Overhead allowed on costs = 610.09 Subtotal of Costs + Overhead = 6,710.94 5% Profit allowed on Costs + Overhead = 335.55 Total for this change = 7,046.48 7,046.49 Jcl SECTION 01 26 55 FORM FOR PRICE OF WORK SBC Project Number: Project Name: CO#1 EAST HICKMAN HS AG BLDG GAS RELOCATION PRICING Work itemized below provided by: David Valentine Proposal Number: CO#1 Date Itemized: 30-Dec-25 Page 1 of 1 pages Description Material Equipment Labor Quantity Unit Cost Extension Quantity Unit Cost Extension Quantity Unit Cost Extension 2" ANODELESS RISER 1 EA 286.81 286.81 0.00 0.00 0.00 0.00 2" STAB 90 1 EA 277.59 277.59 2" STAB COUPLING 1 EA 179.42 179.42 0.00 0.00 TRACER WIRE 1 ROLL 205.00 205.00 0.00 0.00 MAGNETIC LOCATOR TAPI 1 ROLL 75.38 75.38 0.00 0.00 2" YELLOW GAS PIPE 150 FT 3.79 568.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 MINI EXCAVATOR 0.00 2 DAY 300.00 600.00 0.00 SKIDSTEER 0.00 2 DAY 300.00 600.00 0.00 DIESEL HEATER 0.00 3 DAY 200.00 600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PLUMBER 0.00 0.00 24 65.00 1,560.00 PLUMBER HELPER 0.00 0.00 24 55.00 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 Materials Subtotal 1,592.70 Equipment Labor Subtotal 2,880.00 9.750 % Sales Tax = 155.29 33.0 % Burden = 950.40 Cost: 1,747.99 Cost: 1,800.00 Cost: 3,830.40 Subtotal of Costs of Materials + Equipment + Labor = $ 7,378.39 10% Overhead allowed on costs = $ 737.84 Subtotal of Costs + Overhead = $ 8,116.23 5% Profit allowed on Costs + Overhead = $ 405.81 Total for this change = $ 8,522.04 Jd 8,522.00 Posted in XLS format Form for Price of Work July 2012 OFD s012655 01 26 55 - 1 Page 1 of 1 01 26 54 - FORM FOR PRICE SUMMARY SBC Project Number: Project Name: East Hickman Vocational Building Name of General Contractor: Fellowship Construction Proposal Number: RFP 2 Date Itemized: 31-Dec-25 Page of pages Work by Subcontractors Name of Subcontractor Costs and Allowances Move Gas Line Schaffer Plumbing 8,522.00 Subtotal: 8,522.00 General Contractor mark-up on Subtotal: 10.0000 % = 852.20 Subtotal for General Contractor for work by subcontractors: 9,374.20 Work by General Contractor Subtotal (including Subcontractors and the General Contractor): 9,374.20 Cells with red underline (if viewed in color) Bond Premium: 2.0000 % = 187.48 are for you to fill in. Others are protected. Rounding off is permitted if rounding up for decreases and rounding down Total: 9,561.68 for increases. Math functions in Excel show rounded to nearest penny, but carry exact value for calculations. Let embedded math do its work. This spreadsheet is available on the Owner's Designers' Manual website. TN Higher Education - Standard Document - May 2018 Page 1of 1 ## Table 1 | The original was | $ 580,000.00 | | --- | --- | | The net change by previously authorized Change Orders | $ 5,433.92 | | The prior to this Change Order was | $ 585,433.92 | | The will be increased by this Change Order in the amount of | $ 17,467.84 | | The new including this Change Order will be | $ 602,901.76 | ## Table 2 | ARCHITECT (Signature) | CONTRACTOR (Signature) | OWNER (Signature) | | --- | --- | --- | | Bradley A. Martin, III | Irwin Pres. | | | (Printed name, title, and license number if required) | (Printed name and title) | (Printed name and title) | | January 6, 2026 | 1-08-2026 | | | Date | Date | Date | ## Table 3 | 1. Relocate Gas | Add $9,561.68 | | --- | --- | | 2. Relocate Electrical | Add $7,906.16 Total Add: $17,467.84 | ## Table 4 | Work by Subcontractors | Name of Subcontractor | Costs and Allowances | | --- | --- | --- | | Move Conduit for exsiting light poles | Optimal Electric | 5,969.89 | | Add another 2 inch conduit in trench | Optimal Electric | 1,076.60 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ## Table 5 | Description | | | Material | | | | Equipment | | | | Labor | | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | | Qty | Unit | Cost | Extension | Qty | Unit | Cost | Extension | Qty | Unit | Cost | Extension | | extra 2" conduit in the ditch with the 2-2" already speced in the drawings | 1 | | 652.00 | 652.00 | | | | 0.00 | | | | 0.00 | | Labor to install (Electrician | 2) | | | 0.00 | | | | 0.00 | 4 | | 47.43 | 189.72 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | existing pole lighting conduit outside the new facility footer | 1 | | 1,364.00 | 1,364.00 | | | | 0.00 | | | | 0.00 | | Electrician 1 | | | | 0.00 | | | | 0.00 | 16 | | 65.95 | 1,055.20 | | Electrician 2 | | | | 0.00 | | | | 0.00 | 12 | | 47.73 | 572.76 | | Mini ex/Skidsteer | | | | 0.00 | 1 | | 1,803.00 | 1,803.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0,00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | 0 | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0,00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | ## Table 6 | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | Materials | | Subtotal | 2,016.00 | Equipment | | | | Labor | | Subtotal | 1,817.68 | | | 9.5 | % | Sales Tax | 191.52 | | | | | 15 | % | Burden | 272.65 | | | | | Cost | 2,207.52 | | | Cost | 1,803.00 | | | Cost: | 2,090.33 | ## Table 7 | of Costs of Materials + Equipment + Labor = | 6,100.85 | | --- | --- | | 10% Overhead allowed on costs = | 610.09 | | Subtotal of Costs + Overhead = | 6,710.94 | | 5% Profit allowed on Costs + Overhead = | 335.55 | | Total for this change = | 7,046.48 | ## Table 8 | SBC Project Number: | Project Name: | | --- | --- | | CO#1 | EAST HICKMAN HS AG BLDG GAS RELOCATION PRICING | ## Table 9 | Description | | | Material | | | | Equipment | | | | Labor | | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | | Quantity | Unit | Cost | Extension | Quantity | Unit | Cost | Extension | Quantity | Unit | Cost | Extension | | 2" ANODELESS RISER | 1 | EA | 286.81 | 286.81 | | | | 0.00 | | | | 0.00 | | 2" STAB 90 | 1 | EA | 277.59 | 277.59 | | | | 0.00 | | | | 0.00 | | 2" STAB COUPLING | 1 | EA | 179.42 | 179.42 | | | | 0.00 | | | | 0.00 | | TRACER WIRE | 1 | ROLL | 205.00 | 205.00 | | | | 0.00 | | | | 0.00 | | MAGNETIC LOCATOR TAPI | 1 | ROLL | 75.38 | 75.38 | | | | 0.00 | | | | 0.00 | | 2" YELLOW GAS PIPE | 150 | FT | 3.79 | 568.50 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | MINI EXCAVATOR | | | | 0.00 | 2 | DAY | 300.00 | 600.00 | | | | 0.00 | | SKIDSTEER | | | | 0.00 | 2 | DAY | 300.00 | 600.00 | | | | 0.00 | | DIESEL HEATER | | | | 0.00 | 3 | DAY | 200.00 | 600.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | PLUMBER | | | | 0.00 | | | | 0.00 | 24 | | 65.00 | 1,560.00 | | PLUMBER HELPER | | | | 0.00 | | | | 0.00 | 24 | | 55.00 | 1,320.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | | | | | | 0.00 | | | | 0.00 | | | | 0.00 | ## Table 10 | Labor Subtotal | 2,880.00 | | --- | --- | | 33.0 % Burden = | 950.40 | | Cost: | 3,830.40 | ## Table 11 | Subtotal of Costs of Materials + Equipment + Labor = | $ 7,378.39 | | --- | --- | | 10% Overhead allowed on costs = | $ 737.84 | | Subtotal of Costs + Overhead = | $ 8,116.23 | | 5% Profit allowed on Costs + Overhead = | $ 405.81 | | Total for this change = | $ 8,522.04 | ## Table 12 | Work by Subcontractors | Name of Subcontractor | Costs and Allowances | | --- | --- | --- | | Move Gas Line | Schaffer Plumbing | 8,522.00 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |